February 28 to March 7 - Week 6 & 7 Spring 2018

A new design revision will need to be made for our track design. Instead of incorporating an L shaped column design to mount the track system, we will have to revert to the old concepts of a U shape with vertical supports on both sides of the track. This will be done to ensure that including the solar panel system would not affect the structure under high wind conditions. In addition, the height will be adjusted to 2.5 meters to clear the bogie system better.

After these changes are made, the 2D reference drawings will be completed using ordinate dimensioning and sent to Vanderbend for manufacturing. These drawings will be completed by the end of the week.