January 31 - Week 2 Spring 2018

This week we had our lightning talk. We went over our progress from last semester and discussed anything else that we had not completed so far for the track. After the presentations, we contacted our client Futran in order to get a better understanding and idea for the funding and project specifications. They have requested a scope of work which we are working on, detailing our current designs, timeline of completion for these designs, and the budgeting required to manufacture these parts. All designs and progress from now on will need to be logged for R&D, and must have a manufacturability analysis in order for Vanderbend to produce. Many other problems will need to be addressed such as vibration analysis, grounding solutions, wire management, and FEA for the track assembly.