September 20, 2017 - Week 4

Today my team (Full-Scale Track Section) gave a presentation for the rundown on our specific project. We discussed past research, problems to overcome, project planning, and many other design obstacles that we will need to consider for our team. Below is the full presentation:



After the presentations, we discussed with Ron Swenson about the project specifications and has mentioned that the SolidWorks drawings will be uploaded later this week. During the meeting, Ron mentioned the possibilities of integrating certain infrastructure like water pipes, power cables, and other tubing on the outsides of the vertical supports. There will also need to be diagonal bracing/trussing along the vertical supports.

futran-system-presentation-sept-2015-11-638.jpgScreen Shot 2017-09-16 at 9.16.51 PM.png


In addition to these requirements, the track will need to be designed so that it can be easily assembled and disassembled. This will make things easier later on during production when we will need to constantly adjust sections, and add parts during assembly of other team's parts such as solar panels and bogie systems.

The ideal module of length for the track section will be in increments of 3 meter segments. Dealing with space restraints, we may possibly be unable to build a full 18 meter track section. Because of this, it will be more ideal to restrict the length of the track to 15 meters or 12 meters.

The final subject Ron conveyed dealt with the assembly and production of the track parts. Instead of the conventional methods of welding and bending, which can compromise the structural integrity of our track, we were told to look into plasma cutting. This would be able to maintain the composition of our materials used as opposed to welding, bending, or heat treatment which could affect its material properties.